Title 24 Acceptance Testing by System

Each testable system has its own NRCA form. This is the map from what a project installs to which certificate it produces, and which certification the tester needs.

Mechanical systems

  • Outdoor air — NRCA-MCH-02-A
  • Air economizer controls and exhaust — NRCA-MCH-05-A, one per system
  • Hydronic system variable flow — NRCA-MCH-10-A
  • Energy management control system — NRCA-MCH-18-A
  • Heat recovery and energy recovery ventilation — NRCA-MCH-23-A

Lighting systems

  • Occupant sensing and automatic time switch — NRCA-LTI-02-A
  • Daylight responsive controls — NRCA-LTI-03-A
  • Demand response controls — NRCA-LTI-04-A
  • Outdoor lighting controls — NRCA-LTO-02-A

How to read a form name

The pattern carries three pieces of information. NRCA is the certificate family. The next letters are the discipline — MCH for mechanical, LTI for indoor lighting, LTO for outdoor lighting. The trailing letter is who may test: -A a certified acceptance test technician, -F a field technician.

Using this at design stage

Read the list against the equipment and controls schedule before construction starts. Every line that matches is a site visit, a certified technician and a document that has to exist before the permit closes. Projects that discover this at final inspection are not short a form — they are short the work the form records.

It is also a design lever. A scheme that avoids a testable measure avoids its test, and that is a legitimate choice to make deliberately rather than by accident.

Common Title 24 Questions

  1. When is mechanical acceptance testing required?
  2. What is Title 24 lighting acceptance testing?
  3. Who can perform Title 24 acceptance testing?
  4. What happens if acceptance testing fails?
  5. When does Title 24 acceptance testing happen?