A wood-framed floor over a crawl space needs R-19, or U-0.037, in every climate zone. Floor insulation can be omitted only for a controlled-ventilation or unvented crawl space that meets four conditions: insulated foundation walls, a vapor retarder over the earth, temperature-actuated vent louvers and the criteria in Appendix RA4.5.1.
- Choose your report
- Upload your plans
- Pay securely
- Permit-ready report by email
Which crawl space do you have
With ordinary vents, the floor above is insulated like any raised floor, R-19 between the joists. A controlled-ventilation or unvented crawl space can take a different route, in which the walls around the crawl space are insulated instead of the floor above it.
The four conditions for omitting floor insulation
- The foundation walls are insulated to the wall minimums in Table 150.1-A.
- A Class I or Class II vapor retarder covers the entire crawl space floor.
- Vents to the outside have automatically operated, temperature-actuated louvers.
- The criteria in Residential Appendix RA4.5.1 are met.
Section 150.0(d) and Section 150.1(c)1C carry the same conditions, so the route works under the mandatory and prescriptive rules alike.
What Appendix RA4.5.1 adds
- The dampers must be shown on the plans, fully closed at about 40 degrees Fahrenheit and fully open at about 70.
- Vent area is reasonably distributed between opposing foundation walls for cross ventilation.
- Foam touching the earth must be closed-cell and water resistant, meeting the 0.3 percent absorption and 2.0 perm per inch limits that apply to slab edge insulation.
- Eligibility is at the enforcement officials' discretion. Where the site has drainage doubts, the applicant must prove the drainage will work.
The vapor retarder is not optional
Section 150.0(g)1 requires a Class I or II retarder over the earth floor of an unvented crawl space in all 16 zones, and extends the same rule to a controlled-ventilation crawl space that uses the exception.
When you are altering, not building
The manual's alterations table lists adding raised floor insulation at R-19 or an equivalent U-factor, with the exception for floors over controlled-ventilation or unvented crawl spaces. The floor itself is covered on raised floor insulation, and the full package on insulation requirements. Lower-level conversions are on basement conversions. Our residential Title 24 reports start from the plans.
Common Title 24 Questions
- When is Title 24 required for a home?
- Does a remodel need Title 24?
- Does a room addition need Title 24?
- What plans are needed for a residential Title 24 report?
- How much does a residential Title 24 report cost?
- How long does a residential Title 24 report take?
Frequently Asked Questions
Yes. The exception is limited to controlled-ventilation and unvented crawl spaces, and a vented one takes R-19 or U-0.037 under the floor.
The enforcement agency. Appendix RA4.5.1 leaves eligibility to its officials and puts the burden of proving drainage on the applicant.
Explore Insulation
- Is a Blower Door Test Required in California? Title 24 Air Leakage Testing
- QII for Attic Insulation: Rulers, Baffles, Hard Covers and Weight Checks
- QII Wall Insulation Inspection: What the ECC-Rater Checks Before Drywall
- What Is Quality Insulation Installation (QII)?
- Radiant Barrier Requirements Under Title 24
View all Insulation guides → · Windows and Building Envelope · Title 24 guide